Plan documents
Plan documents schedule the work a decision, or a set of decisions, has committed to. They answer the question "what's next, in what order?" — and they answer it durably, in a place that doesn't rot the way a TODO list or a draft Pull Request (PR) description does.
What a plan is
A plan doc is a scheduling doc, not a design doc. The current design lives in the architecture reference and the rationale in decision records. The plan organises the implementation of those decisions into:
- Phases with entry and exit criteria
- Workstreams (often abbreviated WS with a numeric or alphabetic suffix, e.g.
WS1,WS-P1.1) that can sometimes run in parallel - A status section that's updated in place as work lands
The shape varies. A small project might have a single docs/plans/roadmap.md. A larger one accumulates per-phase plans and a top-level roadmap that orders them.
What a plan is not
- Not a decision. "We chose X over Y because Z" → a decision record. The plan consumes that decision and slices it into work.
- Not a handoff. "What needs to happen tomorrow morning, with verification commands" → a handoff. The plan is the persistent layer the handoff folds into at resolution.
- Not an area doc. "How the X subsystem works today" → the architecture reference. The plan refers to it; it doesn't reproduce it.
Anatomy of a good plan
Plans tend to settle into this shape:
# Plan — <Phase / topic>: <one-line goal>
**Status:** <Proposed | Active | Implemented (YYYY-MM-DD)>. <Latest dated update.>
## Goal
What this phase / topic delivers, in 1–3 sentences.
## Prerequisites
What must be true / accepted / merged before this can start. Decisions
that need to be Accepted, fixtures that need to be in place.
## Where things stand (YYYY-MM-DD)
The single most-recent status snapshot. Updated in place.
Past states are in `git log`, not stacked here.
## Workstreams
### WS1 — <Name>
**Status:** <In flight | Shipped commit `abc1234` | Blocked on X>
<Concrete scope. Reference decisions and area docs; don't duplicate them.>
**Deliverables:**
- Specific artefacts: a binary, a schema, a CI gate, a test fixture.
**Exit criteria:**
- Verifiable conditions for declaring this workstream done.
### WS2 — <Name>
...
## Phase exit criteria
A short checklist of bullets. When all are true, the phase closes.
Why entry/exit criteria matter
Plans without exit criteria become forever documents. Someone always thinks of one more thing to add. The exit criteria are the contract: when these are met, the phase closes and a new plan (or follow-up roadmap) takes over.
A useful pattern: the next plan's prerequisites and the current plan's exit criteria mirror each other. That makes the handoff between phases explicit.
Archiving a finished plan
When a plan's exit criteria are all met, set its status to Implemented (YYYY-MM-DD) and move it to docs/plans/archive/. Don't delete it. The phasing and the commit trail are worth recovering later. But a finished plan sitting next to the active ones makes a reader work out which is which, so it moves out of the way.
Moving a file breaks every relative link to it, and every relative link from it. Use the archive tool so both directions get repointed in one step:
uv run docs/scripts/doctool.py archive docs/plans/<plan>.md
It git mvs the file into archive/, rewrites links across docs/, CLAUDE.md, and README.md, and re-depths the moved file's own links. Then update the plans index (and SUMMARY.md, if you render a book) to list the plan under a "Completed plans" heading. Before the move, fold anything still live in the plan into its successor or into the area doc's Implementation status.
The same tool archives a superseded decision (docs/architecture/decisions/NNNN-….md).
Workstream sizing
The right workstream size is "a contributor can pick this up cold and start within an hour." Anything larger and it's really a phase. Anything smaller and it's really a task that belongs in a handoff.
A workstream typically has:
- A short name (
WS-P1.1,WS2.4,WS-RH.1— whatever scheme fits) - 1–3 deliverables
- An exit criterion you can test for
- An effort estimate ("~2 days", "~1 week")
Updating a plan
Plans are updated in place as work lands. A common pattern:
### WS-P1.1 — Structured timing output
- **WS-P1.1.a — Symbolic violation messages.** **Shipped 2026-05-02 in commit `0432d9a`.** New `WordSymbolMap` ...
- **WS-P1.1.b — `--timing-report <path.json>`.** **Shipped 2026-05-02 in commit `58a7a04`.** ...
- **WS-P1.1.c — `--timing-summary` text output.** **Shipped 2026-05-02 in commit `44e70a0`.** ...
- **WS-P1.1.d — Per-DFF worst-slack ranking.** Partially shipped in `58a7a04`. Remaining: ...
The pattern: bold the status, name the commit, say what shipped. The plan becomes a readable history once enough of it is filled in.
Scheduling vs. design split
A subtle but load-bearing rule: plans schedule; decisions decide; the reference describes.
When you find yourself writing "we chose X over Y because Z" inside a plan, that paragraph belongs in a decision record. When you find yourself writing "the system works by …" inside a plan, that belongs in the area doc.
The plan should reference both without reproducing them: "per Decision 0007, Pillar B Stage 3 lands only if measurement justifies it."
Multiple plans, one roadmap
Once a project has more than two or three active plans, add a roadmap.md that orders them, and a docs/plans/README.md index that lists active plans first and completed ones (in archive/) after. The roadmap doesn't replace the per-phase plans; it sequences them. See Jacquard's post-phase-0-roadmap.md as a real example.
Template
A copy-paste-ready plan template lives at starter/docs/plans/_template.md.