Plan documents

Plan documents schedule the work a decision, or a set of decisions, has committed to. They answer the question "what's next, in what order?" — and they answer it durably, in a place that doesn't rot the way a TODO list or a draft Pull Request (PR) description does.

What a plan is

A plan doc is a scheduling doc, not a design doc. The current design lives in the architecture reference and the rationale in decision records. The plan organises the implementation of those decisions into:

  • Phases with entry and exit criteria
  • Workstreams (often abbreviated WS with a numeric or alphabetic suffix, e.g. WS1, WS-P1.1) that can sometimes run in parallel
  • A status section that's updated in place as work lands

The shape varies. A small project might have a single docs/plans/roadmap.md. A larger one accumulates per-phase plans and a top-level roadmap that orders them.

What a plan is not

  • Not a decision. "We chose X over Y because Z" → a decision record. The plan consumes that decision and slices it into work.
  • Not a handoff. "What needs to happen tomorrow morning, with verification commands" → a handoff. The plan is the persistent layer the handoff folds into at resolution.
  • Not an area doc. "How the X subsystem works today" → the architecture reference. The plan refers to it; it doesn't reproduce it.

Anatomy of a good plan

Plans tend to settle into this shape:

# Plan — <Phase / topic>: <one-line goal>

**Status:** <Proposed | Active | Implemented (YYYY-MM-DD)>. <Latest dated update.>

## Goal

What this phase / topic delivers, in 1–3 sentences.

## Prerequisites

What must be true / accepted / merged before this can start. Decisions
that need to be Accepted, fixtures that need to be in place.

## Where things stand (YYYY-MM-DD)

The single most-recent status snapshot. Updated in place.
Past states are in `git log`, not stacked here.

## Workstreams

### WS1 — <Name>

**Status:** <In flight | Shipped commit `abc1234` | Blocked on X>

<Concrete scope. Reference decisions and area docs; don't duplicate them.>

**Deliverables:**
- Specific artefacts: a binary, a schema, a CI gate, a test fixture.

**Exit criteria:**
- Verifiable conditions for declaring this workstream done.

### WS2 — <Name>

...

## Phase exit criteria

A short checklist of bullets. When all are true, the phase closes.

Why entry/exit criteria matter

Plans without exit criteria become forever documents. Someone always thinks of one more thing to add. The exit criteria are the contract: when these are met, the phase closes and a new plan (or follow-up roadmap) takes over.

A useful pattern: the next plan's prerequisites and the current plan's exit criteria mirror each other. That makes the handoff between phases explicit.

Archiving a finished plan

When a plan's exit criteria are all met, set its status to Implemented (YYYY-MM-DD) and move it to docs/plans/archive/. Don't delete it. The phasing and the commit trail are worth recovering later. But a finished plan sitting next to the active ones makes a reader work out which is which, so it moves out of the way.

Moving a file breaks every relative link to it, and every relative link from it. Use the archive tool so both directions get repointed in one step:

uv run docs/scripts/doctool.py archive docs/plans/<plan>.md

It git mvs the file into archive/, rewrites links across docs/, CLAUDE.md, and README.md, and re-depths the moved file's own links. Then update the plans index (and SUMMARY.md, if you render a book) to list the plan under a "Completed plans" heading. Before the move, fold anything still live in the plan into its successor or into the area doc's Implementation status.

The same tool archives a superseded decision (docs/architecture/decisions/NNNN-….md).

Workstream sizing

The right workstream size is "a contributor can pick this up cold and start within an hour." Anything larger and it's really a phase. Anything smaller and it's really a task that belongs in a handoff.

A workstream typically has:

  • A short name (WS-P1.1, WS2.4, WS-RH.1 — whatever scheme fits)
  • 1–3 deliverables
  • An exit criterion you can test for
  • An effort estimate ("~2 days", "~1 week")

Updating a plan

Plans are updated in place as work lands. A common pattern:

### WS-P1.1 — Structured timing output

- **WS-P1.1.a — Symbolic violation messages.** **Shipped 2026-05-02 in commit `0432d9a`.** New `WordSymbolMap` ...
- **WS-P1.1.b — `--timing-report <path.json>`.** **Shipped 2026-05-02 in commit `58a7a04`.** ...
- **WS-P1.1.c — `--timing-summary` text output.** **Shipped 2026-05-02 in commit `44e70a0`.** ...
- **WS-P1.1.d — Per-DFF worst-slack ranking.** Partially shipped in `58a7a04`. Remaining: ...

The pattern: bold the status, name the commit, say what shipped. The plan becomes a readable history once enough of it is filled in.

Scheduling vs. design split

A subtle but load-bearing rule: plans schedule; decisions decide; the reference describes.

When you find yourself writing "we chose X over Y because Z" inside a plan, that paragraph belongs in a decision record. When you find yourself writing "the system works by …" inside a plan, that belongs in the area doc.

The plan should reference both without reproducing them: "per Decision 0007, Pillar B Stage 3 lands only if measurement justifies it."

Multiple plans, one roadmap

Once a project has more than two or three active plans, add a roadmap.md that orders them, and a docs/plans/README.md index that lists active plans first and completed ones (in archive/) after. The roadmap doesn't replace the per-phase plans; it sequences them. See Jacquard's post-phase-0-roadmap.md as a real example.

Template

A copy-paste-ready plan template lives at starter/docs/plans/_template.md.